Moscow
Kutuzovsky 32, busbar trunking in Building E
Installation of 2,000 A and 2,500 A busbar trunking in an operating building of the business quarter at 32 Kutuzovsky Prospekt, with work at night and at weekends.
- Power supply

The project in numbers
Based on the estimate of our contract; work in progress
Building E of the business quarter on Kutuzovsky Prospekt is the former President Plaza business centre, one of the first buildings of the quarter to open. Our team is now installing busbar trunking in it: two 2,000 A lines inside the building and a 2,500 A line that comes in from the neighbouring Building V. The building stays in operation throughout.
Our scope
- Installation of 2,000 A and 2,500 A busbar trunking.
- Support brackets and hangers under the slabs.
- Fire-rated penetrations through walls and floors.
- Testing of the lines and as-built documentation.
Systems
2,000 A busbar
Two main lines inside Building E: 91 busbar elements, including 28 straight 3 m sections, 90 joint packs, 162 support brackets and 8 fire-rated penetrations.
Equipment: Albimax KLM-S busbar, aluminium, IP68
2,500 A busbar
The line that comes into Building E from Building V: 64 elements, including 27 straight sections, 64 joint packs, 108 support brackets and 8 fire-rated penetrations.
Equipment: Albimax KLM-S busbar, aluminium, IP68
How the work is going
- Survey. We walked the routes of the future lines through the car park and plant rooms and checked them against the working documentation.
- Supports. We are fixing the support brackets under the slabs, ready for sections weighing up to 100 kg.
- Sections and joints. We lift and join the busbar sections and seal the penetrations through walls and floors with fire-rated kits.
- Testing. Every line will be tested and handed over with the as-built documentation.
What makes the project special
- An operating building. In Building E we work at night and at weekends so as not to disrupt the offices.
- Heavy sections. Busbar sections weigh up to 100 kg and are installed overhead.
- IP68 protection. The sealed busbar is protected against dust and water.
- Fire safety. 16 fire-rated penetrations keep the building's fire barriers intact.
Interesting facts
- Building E is the former President Plaza business centre, opened in 2017–2018.
- The business quarter brings together five buildings with a total area of about 585,000 m².
- Construction on the site began in 2006 under the Mirax Plaza project.