Moscow Oil Refinery: electrical installation and lighting

Electrical works at the operating Moscow Oil Refinery: power and lighting for a new administrative complex, 53 km of cable lines and heavy cable on an overpass.

  • Power supply
The Moscow Oil Refinery at sunset

The project in numbers

over 53 kmof cable lines
over 1,425luminaires in the new admin complex
over 1.9 kmof 5×240 mm² power cable
11 mworking height on a live overpass

The scope of our works on the project

Gazprom Neft's Moscow Oil Refinery in Kapotnya covers more than a third of the capital region's demand for motor fuel, including the Moscow airports. Since 2011 the refinery has been undergoing a large-scale modernisation. Our team carried out electrical works at the operating plant: in a new administrative and amenity complex and at the refinery's energy facilities.

Our scope

  • Power supply and power circuits of the new administrative and amenity complex.
  • Indoor and outdoor lighting of the complex.
  • Connection of smoke control dampers to the control system.
  • Power and control cable lines for the refinery's heat and power facilities.
  • 0.4 kV panels, cable supports and trays.
  • Earthing.

Systems

Administrative and amenity complex

A new building with an office block and an amenity block. About 1,425 luminaires mounted at about 4 m, 350 sockets and 245 switches, cable lines from the panels, and outdoor lighting on composite poles.

Equipment: halogen-free and fire-resistant PPGng(A)-HF and FRHF cables, cable trays

Smoke control automation

Connection of fire and smoke dampers through 16 relay units, with about 440 m of cable.

Equipment: Bolid S2000-SP4/220

Refinery energy facilities

Armoured power cable and control cable for the heat and power complex, including about 1.9 km of 5×240 mm² cable on a live cable overpass at a height of 8–11 m. Six 0.4 kV panels, about 1,200 cable shelves and posts, 32 cable terminations and sealed cable entries into hazardous-area rooms.

Equipment: VBbShvng(A)-LS and KVVGng(A)-LS cables, KVT terminations, Layher scaffolding

How the work went

  1. Clearance for the refinery. In May 2025 the crew passed industrial safety tests and received passes to the operating plant.
  2. The new administrative complex. We laid cable lines and installed lighting in the new building, more than 1,400 luminaires.
  3. Heavy cable above the plant. We pulled 5×240 mm² power cable along a live overpass at 8–11 m, from an aerial platform and scaffolding, over rollers and with a winch.
  4. Panels and connections. We installed the 0.4 kV panels, terminated the cables and connected the equipment.

What made the project special

  • An operating refinery. Work on the site of a running plant under permits to work, with gas detectors and respiratory protection.
  • Heavy cable at height. One metre of 5×240 cable weighs about 15 kg. It was winched over rollers at 8–11 m.
  • Engineering judgement. We calculated the extra load on the old overpass and had it strengthened before the cable was pulled.
  • Industrial safety. Staff certification, permits for work at height and hot work, method statements.

Interesting facts

  • The refinery processed its first tonne of crude on 1 April 1938, which is considered its birthday.
  • In 1941 a plywood double of the refinery was built a few kilometres away to deceive enemy aircraft.
  • The Euro+ complex, launched in 2020, replaced five 1960s units and provides half of the refinery's capacity.
  • The Biosphere treatment facilities clean wastewater to 99.9% and cut water intake from the Moskva River by 2.5–3 times.

Photos: kishjar?, Flickr, CC BY 2.0